This is a very exciting time at Nardin with all the work that is underway on the new facilities.  Work continues on the gymnasium and health & wellness center located on Cleveland Avenue.  Windows are currently being installed, and the masons are on site daily as the bricks are being put up on the outside.  As exciting as the work is on the exterior, there is much happening on the inside of the new building too.  Drywall is being installed, and we anticipate painting and tile-work to begin in the coming weeks.  As of now, the schedule has the lights, remaining fixtures, and gymnasium flooring scheduled to be installed in March/April.  Similarly, the work on the new fields on Elmwood is progressing.  The site is ready for the turf, lighting, and scoreboard to be installed as soon as the weather cooperates.  Let’s hope for an early spring!